CopyrightThis collection is accessible under an assertion of fair use for purposes of research, education, and scholarship. Some items in this collection may be protected by copyright law (Title 17, U.S.C.). Transmission or reproduction of materials protected by copyright beyond that allowed by fair use requires the written permission of copyright owners. Responsibility of their use rests entirely on the individual. The Indianapolis Museum of Art does not own copyright to these materials, however, the IMA has made every effort to provide accurate information about the copyright holder whenever possible. The IMA is eager to hear from any copyright owners so the IMA can provide the appropriate information to interested researchers. If you have information please contact the Indianapolis Museum of Art Archives, 4000 Michigan Rd., Indianapolis, IN 46208 or archives@imamuseum.org.
December 28, 1956
Mr. Irwin Miller
301 Washington Street
Columbus, Indiana
Re: Miller House
Dear M. Miller:
When I met on the job early this month with Mr. Newlin and Mr. Taylor, there was some suggestion that the job was not progressing because the contractor felt he was being forced to do work in excess of his contract.
It was agreed that he would submit a list of such work and I am enclosing a copy of his letter and offering the following comments on it.
Item 1. This is a fair price for the work. It is our feeling that it is not a legitimate extra and under normal circumstances we would not allow it to be proposed. We are subscribing to it now only in the interests of saving time.
Item 2. This is a legitimate extra for this change.
Item 3. Virgil's dates do not tell the whole story on this one. The final proposal was prepared between September 26 and October 5.
Actually you approved the final proposal on October 1, subject to certain modifications. We advised Virgil, by letter, of this on October 2 and instructed him to proceed with the work. We received the final adjusted quotation from him on October 5 and as I assumed that it had clearly understood that he was to proceed with the work, I waited until I had a number of other items to discuss with you before sending him a formal letter.
Since it should have been obvious when he priced it that the work could not be finished before cold weather, this extra can only proposed as an inducement to Virgil to expedite the job.
Item 4. This is for some additional finishing by Foss and is fair.
Sincerely,
EERO SAARINEN AND ASSOCAITES
Kevin Roche
KR: mir
Content Disclaimer and Usage Rights
Metadata about Newfields’ Archives collections comes from Newfields’ records and research. In some cases, information may be incomplete and research is ongoing. Newfields’ goal is to have as up-to-date metadata as possible, therefore, this information is subject to change. Newfields collections’ metadata is available under a Creative Commons Zero (CC0) waiver, which allows for re-use without legal restrictions.
The content the image file(s) above may be in copyright or have other legal and/or cultural restrictions to their use. For clarity, Newfields does not claim copyright to the image files created by Newfields of materials in Newfields Archives collections. Newfields makes every effort to ascertain the copyright status of materials in Newfields’ Archives collections. Please refer to the RightsStatement.org statement above for information about the current copyright status of the content the image file(s).
Additional information about Newfields Archives reproduction guidelines can be found in the Archive Reproductions.